Four sewage treatment plant in Gansu
Author:admin Date:2010-05-02 12:23:44 Views:11671
【Close】
Recently, the General Office of Gansu Provincial Government informed the first quarter of 2009, letters of responsibility for the provincial government to implement environmental objectives and progress in pollution reduction. Communications showed a quarter of the province of life in 14 garbage treatment plants have been built to run well, sewage treatment plant run rate of 100%, but the pipeline still not complete and other issues.
Issue a financial stumbling block
Lanzhou sewage "full collection of" slow progress of the works
Currently, the province's 50 works arranged in emission reduction projects have been completed and passed the acceptance one, have been built in 13, started construction of 18, not 18 under construction, part of the key emission reduction projects has been slow. Urban infrastructure and key pollution control projects are severely underfunded. Among them, the Lanzhou City sewage "all collection" pipeline construction project estimated 995.4 million yuan investment, wild goose Bay Sewage Treatment Plant Expansion project estimated investment 400 million yuan, construction funds for two projects were not implemented. If not completed on schedule, will directly affect the chemical oxygen demand throughout the province this year and next task to achieve emission reduction targets.
Second, environmental law issues
Waste-water treatment still exists
March 31, the ministry center for the Northwest Environmental Inspector Inspector day, and found peace Qilihe District of Lanzhou City sewage treatment plant sewage treatment facilities can not function properly, excessive discharge of sewage. In addition, due to lack of necessary monitoring equipment, the province's 102 county-level environmental agencies can not reach the "national institution-building environmental monitoring and surveillance standard" requirements, affect the normal regulation and disposal of environmental emergencies.
To the three heat transport is difficult
Pipeline pressure is not complete pollution reduction
Lanzhou City, the East West heat output heating project has completed an investment of about 75 million yuan, the new heating an area of 700,000 square meters, but not supporting pipe network, heat can not transport, resulting in increased pressure on pollution reduction in Lanzhou City. Also part of the duty not to implement the emission reduction units (scheduled for the West Wastewater Treatment Plant can not be stable discharge standards, etc.). A quarter of the province a total of 69 countries focused on pollution control is not installed on-line monitoring system, in which there are 10 in Lanzhou.
Deadline for correction
Completed before the end of four sewage treatment plant
Briefing also highlighted the problem of urban sewage treatment plant proposed corrective measures, listed in the schedule:
Ning - Qilihe sewage treatment works: the actual capacity of the current 9 tons / day or so, through the improvement of sewage collection pipe network, reaching 160 thousand tons / day capacity;
Wild goose Bay Sewage Treatment Plant Expansion Project: the project is completed, the processing capacity of 260,000 tons / day;
West-solid sewage treatment plant under construction: After the completion of processing capacity of 100,000 tons / day;
Yanchangbu sewage treatment plant under construction: After the completion of processing capacity of 40,000 tons / day.
According to the provincial government request, the four key projects to be completed in December this year.
Editor: Wei Xiang
Comment
Two sewage overflow to clear the sewage and then injured the mother river 2009-06-08 2009-05-15 wild goose Bay Sewage Treatment Plant Expansion 2009-05-15 Accumulate Chang will highlight the "big four" power 2009-05-12 sewage "extinguished" street repaired 2009-05-11 sewage into the river is not out into the public water supply is not 2009-04-23 No charges 2009-04-09 sewage treatment effluent wells no longer flow under the clear 2009-03-30